FAQs
- Some noise, dust & vibration
- Brief heavy plant movement
- Additional vehicles being parked
Will I still be able to access my rear garden through the new site?
Yes, once the new homes are built, access will remain the same. During construction access will be restricted.
How many car parking spaces will be available?
Across both sites there will be 44 car parking spaces provided (26 on north site, 18 on south site).
When could construction start?
The procurement for a main construction contractor will begin shortly. We anticipate works could start as early as April 2027.
Will we be inconvenienced whilst the works are being carried out?
We will ensure any inconvenience during construction is kept to a minimum. The contractor we employ will be a member of the Considerate Contractor Scheme - https://www.ccscheme.org.uk/. Below are items we are aware may cause potential disruption, however these will be managed and mitigated by Thurrock Council:
How long will the works take?
We anticipate construction will last approximately 12 months.